07/29/2023
WEEK Two: Monday, July 31st thru Sunday, August 6th
If you plan on flying during Week Two of the project, July 31st through August 6th you MUST move your aircraft to the designated temporary
tie-down area shown on the attached exhibit, in light orange- no later than Sunday, July 30th, 9:00Pm.
Harvey Field will not provide anchors or tie downs.
The gate for access to and from the “aircraft temporary tie-down area” location off Airport Way will be opened during airport business hours of operation and locked outside those hours (6:00am-9pm.)
Runway 15R/33L is closed and will be used as a temporary taxiway during the duration of the project. NOTAM has been filed.
Taxiway Alpha and the Main Ramp will be closed: Monday, July 31st thru Wednesday August, 3rd for Crack sealing, Fog sealing and Pavement Markings will take place on the main ramp and taxiway Alpha.
NOTAM has been filed.
Taxilanes: will be closed August 2nd thru Sunday, August 6th to vehicle and aircraft traffic during phase two of Construction: Crack sealing, Fog sealing and Pavement Markings will take place on ALL Taxilanes East of the Main Ramp and Taxiway Alpha.
Runway 15R/33L: is closed and will be used as a temporary taxiway during the duration of the project. NOTAM has been filed.
Barricades will be placed by the Contractor blocking areas under construction and removed once determined safe for taxiing aircraft.
The project will provide rehabilitation of existing pavement on the main apron, Taxiway A, and approximately 15 Taxilanes at Harvey Field. Major work elements include crack sealing, fog seal coat, and new pavement markings. Some small, localized areas showing moderate pavement distress will be repaired using a mastic seal coat. This project will extend the useful life of the airfield pavements and reduce overall life cycle rehabilitation costs.
Please watch for NOTAMS regarding closures -during Phase Two.
If you have any questions or concerns, please email [email protected]
The Harvey Family and Staff would like to “Thank you” for your continued support during the rehabilitation project.
Improving and maintaining S43, in partnership with you, one project at a time.