Today’s project involved the removal of a 550-gallon underground oil tank, along with the excavation of contaminated soil discovered beneath the tank.
One unique challenge? The homes addition directly over the area where the tank was located. To safely complete the remediation, our team installed helical piers to properly support the structure while we excavated beneath it.
This is where experience matters. Environmental remediation isn’t just about digging soil—it’s about understanding structural impacts, engineering solutions, and getting the job done safely.
✅ 550-Gallon Tank Removed
✅ Soil Remediation Completed
✅ Helical Piers Installed for Structural Support
✅ Addition Protected During Excavation
✅ One Less Environmental Concern for the Homeowner