07/06/2017
Just some information about the hwy 84 project. Please drive safe during the construction!
The project work schedule is as follows;
Project Start Date: Monday August 14, 2017 with an thirty-eight day duration
Culvert Work start: Monday August 14, 2017 with a five day duration
Paving/Milling start: Monday August 21, 2017 with a fourteen day duration
Agg. Shld.’ing start: Monday September 11, 2017 with a five day duration
Guardrail start: Tuesday September 19, 2017 with a four day duration
Rumble’s & Paint full length start: Monday September 25, 2017 with a eight day duration
Completion date: Tuesday October 5, 2017
The planned week is 5 days, Monday through Friday, but Saturdays will be used to fill in rain days.
The Contractor is Knife River Materials.
The culvert operation will be done with short term lane closures. One maybe two days with the closures removed for night hours. The mill & fill operation will have a flagger and pilot car operation for the paving. The Shouldering operation will be a flagger guarded short duration operation. The guardrail will be short term lane closures day light hours only. The rumble strips & painting will then use a mobile operation traffic control