09/04/2026
Week 5 of the Taxiway B, Phase 2 project update. The “hand pour” sections and a few light bases are the final remaining concrete areas that need to be put in place. Dirt work, more electrical work, and painting are on the books for next week. It is anticipated that our main runway, Runway 1/19, will reopen September 11th allowing for normal operations to return. Please watch NOTAMs for the latest updates.