Sg MRT Construction

Directions Website Contact the business

Sg MRT Construction Just a few enthusiasts and a passion project. Not affiliated with the Land Transport Authority (LTA)

With the haze gradually worsening over the past month, we haven't been out and about as much as usual. Nonetheless, pass...
27/09/2026

With the haze gradually worsening over the past month, we haven't been out and about as much as usual. Nonetheless, passing by a worksite while on a train provided an excellent opportunity to observe the progress of works while remaining out of the haze. The site we're talking about was none other than that of the future Sungei Kadut station on the DTL2e project.

Works here were still at the site clearing stage, being performed under an advanced works contract - contract 9177. Much of the area has since been cleared of the former factories and warehouses, but there still remain 2 office buildings that were built later on and are newer concrete-based buildings that were being progressively demolished. As such, actual construction works for the project's permanent structures had not begun yet.

A little further south, the site for contract 991, which is for the construction of tunnels connecting DE1 & DE2 stations to the Gali Batu depot, had been handed over to the contractor. Heavy machinery had been mobilised on site ahead of the works kicking off.

And to round off the update, contractor for the DE1 intermediate station under contract 992 - Woh Hup - had recently released a few new renders of the station on their website. There were some minor design alterations, but the structure of the station is kept largely the same.

In addition to all the above, Telegram groups for the contractors to push out message and updates to relevant stakeholders have been created. Find the links to these groups and more images on the DTL Construction Blog - link in bio.

https://downtown-line.blogspot.com/2026/09/dtl2e-recap-in-august-2026.html

Works are moving along across the first three announced sections of the CRL in phase 1, phase 2 and the Punggol Extensio...
13/09/2026

Works are moving along across the first three announced sections of the CRL in phase 1, phase 2 and the Punggol Extension. Due to time constraints, the CRL snapshot for August 2026 only focuses on a few stations across each section.

In phase 1, existing station modification works were in full swing over at Hougang and Ang Mo Kio stations. Pasir Ris and Bright Hill, the other two interchange stations along the phase, have seen less visible work done. Hougang station is where the work is most apparent, with the existing lift being decommissioned for upgrading works since Q3 2025. The refurbished lift is targeted to commence service in October, allowing station modification works to proceed into stage 3. Currently, works were kicking off for stage 2 of the modifications, with additional hoarding going up at the southern portion of the station.

At Ang Mo Kio, parts of the former retail space near Exit A had been converted into new public toilet facilities. These had yet to be commissioned as of the end of August, but will replace the existing toilet facilities. Doing so would allow for the space near the existing Exit D to be taken over for construction of the paid transfer link and conversion into Exits 2 & 6.

Along the CPE, concurrent diaphragm wall construction and excavation works were underway at both Riviera and Punggol stations. Tunneling works had also progressed through the first major junction after leaving the Riviera station box.

Finally, along phase 2, the TBMs for contract CR210 had been lowered into the launch shaft. Only the back up gantries and a single corkscrew conveyor remained at surface level. Diaphragm wall works continued on within the Jurong Lake District station site.

For more photos and full details, do drop by the CRL Construction Blog - link in bio.

https://crl-construction.blogspot.com/2026/09/crl-snapshot-in-august-2026.html

We're kicking off September with a snapshot recap of the JRL progress in August. It's been a while since we covered the ...
05/09/2026

We're kicking off September with a snapshot recap of the JRL progress in August. It's been a while since we covered the entire line and are glad that we managed to do so this past month. Works along phase 1 have progressed sufficiently that individual station liveries are beginning to make an appearance. Would you be able to identify the stations based on their liveries?

In another significant update, all phase 1 stations have already received or are undergoing Platform Screen Gate (PSG) installation. The complete installation of these gates across phase 1 would signal the section drawing closer to completion and the potential for test and trial running to begin. Ongoing works include the installation of noise barrier panels as well as station exterior facade installation.

Along phase 2, works are progressing along as well. Stations under contract J108 are likewise beginning to show individual liveries while viaduct span construction under contract J109 was close to wrapping up. Installation of escalators was underway at the three stations in this contract.

And finally, phase 3 was another mixed bag as well. Most sections had made remarkable progress except those on the southern-most portion of the phase. Viaduct pier and span construction were still in progress here while track-laying works had mostly completed for other sections within the phase.

As always, all the full details and pictures can be found on the JRL Construction Blog - link in bio.

https://jrl-construction.blogspot.com/2026/09/jrl-snapshot-in-august-2026.html

When contract 115 for the construction of the new NS3A Brickland station was awarded in December 2025, the LTA shared th...
29/08/2026

When contract 115 for the construction of the new NS3A Brickland station was awarded in December 2025, the LTA shared that construction works would commence in the first half of 2026. When passing by the site recently, we took the opportunity to view some of the ongoing works.

To date, the site offices for the project are being set up while site preparation works are underway. Earlier in the month, heavy machinery was seen on site but these machines had since been removed towards the month's end. We did observe what might appear to be a test pile ahead of actual construction work commencing. Test piles are used to test the planning assumptions and verify engineering calculations before the final structures are built.

A soil investigation rig was seen, which will also likely help to support the proposed construction method statement developed for the project. Site clearing has yet to begin in earnest at this stage, although this should not be too far off now.

This is an Instagram & Facebook-only post.

Yesterday, the LTA launched the first CRL3 contract for tender - Contract CR306. The contract will likely include the co...
26/08/2026

Yesterday, the LTA launched the first CRL3 contract for tender - Contract CR306. The contract will likely include the construction of a launch shaft, RTS facility building and tunnels connecting to neighbouring stations. As the first contract floated for tender, this also allowed us a better look at the timeline being looked at for completion of the works. According to information on government bidding portal Gebiz, the delivery date for the contract is January 2037, which means that we can expect CRL3 to open for revenue service around that year.

As part of the contract tendering process, interested contractors would need to undergo a second round of pre-qualifications. In September last year, the first round of pre-qualifications was conducted, with 35 companies responding to indicate interest.

This post is also available on the CRL Construction Blog - link in bio.

https://crl-construction.blogspot.com/2026/08/crl3-commencement-of-contract-tendering.html

We're now 4 months in since the Sengkang LRT's West Loop inner track closed for reconstruction works to add new turnouts...
22/08/2026

We're now 4 months in since the Sengkang LRT's West Loop inner track closed for reconstruction works to add new turnouts for a pair of reception tracks connecting to the expanded Sengkang LRT depot. Since then, the new tracks have been connected to the existing main line tracks, with new detection loops added through the switches. The concrete plinths on which the LRT vehicles run have been cast and power rails re-installed.

Works have progressed well and it appears that most of the works to reconfigure the mainline have since been completed. To date though, we have not seen any testing works being carried out yet. As the alignment of the guide rails, power rails and concrete plinth tracks are critical for the safe & smooth operation of the vehicles, test running is an important step to verify that the components are installed as specified and are working together effectively.

We also noticed that the number of temporary enclosure panels installed where the new reception track viaducts crossed over the existing mainline viaducts had decreased. It is likely that removal works were in progress with the bulk of the civil works since completed. All in all, residents of Sengkang have put up with service amendments for 4 months but can now look forward to LRT services coming back online soon.

This is an Instagram & Facebook-only post.

Work on Singapore's longest line - the CRL which will eventually stretch for 67km - has been progressing steadily. Most ...
15/08/2026

Work on Singapore's longest line - the CRL which will eventually stretch for 67km - has been progressing steadily. Most of the stations along Phase 1 have completed diaphragm wall construction, with only a handful left at that stage. Most of the other stations have commenced excavation works with concurrent slab casting taking place. Tunneling works have progressed by leaps and bounds as well, with approximately 86% of the tunneling for Phase 1 completed.

Over along the Punggol Extension, works were progressing along as well with the large diameter TBM successfully tunneling through the site of the future Riviera station and moving onwards towards the Punggol terminal. Over at Punggol, demolition works at the former fare unpaid underpass appear to be completed at the northern end, allowing for reconfiguration works to convert the space into the future Exit 7.

And finally along Phase 2, ERSS construction works were in full swing at most stations. At the Clementi station site, a major traffic diversion was implemented in June, with works to clear the site occupied by the former roadway still in progress. It also appeared that the West Coast station site was gearing up for similar works. Also at the West Coast station site, excavation works at the launch shaft appeared to have begun, with the ERSS equipment no longer present.

For more pictures and videos of the various sites, along with details of the progress made, do drop by the CRL Construction Blog for full details - so much that we couldn't fit in here - link in bio.

https://crl-construction.blogspot.com/2026/08/crl-snapshot-in-july-2026.html

Works on phase 2 of the JRL have been progressing, with works commencing on architectural and mechanical & electrical co...
08/08/2026

Works on phase 2 of the JRL have been progressing, with works commencing on architectural and mechanical & electrical components at some of the stations. Station-specific liveries are beginning to appear and linkbridges connecting to exit podiums have been installed in most stations. In addition, all stations now have had work commence on the installation of roof trusses and roofing installation.

Did you know that Tengah Plantation (JE1) station will feature a livery consisting o Purple & Lilac colours, Tengah Park (JE2) station will feature Red & Purple while Bukit Batok West (JE3) station features Red & Ruby?

For more details on the progress of stations along JRL's Phase 2, do head on over to the JRL Construction Blog for full updates - link in bio.

https://jrl-construction.blogspot.com/2026/08/jrl2-snapshot-in-july-2026.html

Somehow, recent announcements of the locations of new stations on MRT lines seem to lack the punch that they once had. W...
01/08/2026

Somehow, recent announcements of the locations of new stations on MRT lines seem to lack the punch that they once had. Working names for the stations used to be unveiled, glimpses of the potential station designs used to be shown and exits used to be demarcated, giving commuters a rough idea of how the stations might turn out once fully built.

The stations on the CRL's final phase were unveiled yesterday by Minister for Transport .jeffrey but were devoid of the above information - with one exception being the name Gul Circle being shown. We understand this to be due to changes to how the names are received and to cater for potential design changes to the stations when contractors receive the briefs and develop detailed designs later in the process. Nonetheless, we have 4 upcoming stations to anticipate the CRL's arrival in the far west come the late 2030's.

Oh, there'll be an additional depot thrown in as well, as anticipated at the site of the former Raffles Country Club. We recently posted on the advanced works taking place there to prepare the land for the construction to come.

From the basic maps that have been released thus far, two of the stations will feature paid transfers to other lines - namely the JRL at Jurong Pier and the EWL at Gul Circle. The latter is the only name reflected on the map for Phase 3 being that it is an existing operational station with an already established name. Jurong Pier, on the other hand, was retrospectively removed from all publicity materials relating to the JRL and the station (JS12)'s official name has yet to be confirmed.

What are you looking forward to the most in learning about the stations? Let us know in the comments section below.

You can also drop by the CRL Construction Blog to read more about the phase's alignment and official announcement - link in bio.

https://crl-construction.blogspot.com/2026/08/crl3-4-more-stations-and-depot.html

Do you recall that the public were invited to vote on certain design aspects of the CRL trains some time back? These wer...
31/07/2026

Do you recall that the public were invited to vote on certain design aspects of the CRL trains some time back? These were for seat colour schemes, the hand rail well at doorway colour schemes, design of the draught screen panels, floor colour schemes and whether decorative LED feature lights should be included in the train's design.

Today, the SGMC team was graciously hosted by Land Transport Authority – We Keep Your World Moving during the Minister of Transport's visit to the Singapore Rail Test Centre for the unveiling of the CRL train sets in Singapore.

The team was able to board the stationary trains and explore some of the design features within the trains. We can confirm that the seat colours assigned for Cars 1 and 6 will be light blue, with Cars 2 and 5 featuring green and Cars 3 & 4 featuring a dark blue scheme. The train cars are numbered sequentially, with each train set carrying cars numbered 1 through 6.

The hand rail wells of the trains are coloured Lime, the line's colour, for easy identification of the hand rails. For the draught screens, diagonally facing pairs of triangles were chosen. This design was not very obvious and appeared minimalistic, to the point that one might miss the design if one were not looking for it actively. The floors on the other hand, opted for the single tone scheme.

Voters also chose for the wider gangways to feature decorative LED lights, which immediately distinguish the trains from others on the existing operational lines. Some other features include the use of doors with micro plug functions that are supposed to offer better sound insulation within the saloon.

Being powered by an overhead catenary rail system, the trains are equipped with pantographs on Cars 2 and 5. We managed to get a look at these often hard to see components of the trains.

There were so many other features that we got to discover, but unfortunately were not able to fit all into the limited space on Instagram. The full set of pictures, however, can be found on the CRL Construction Blog - link in bio.

https://crl-construction.blogspot.com/2026/07/cr151-preview-of-crl-trains.html

Address

Singapore

Alerts

Be the first to know and let us send you an email when Sg MRT Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Sg MRT Construction:

Shortcuts

Share