06/01/2021
It's about time we put a post on to bring you up to speed on what we have been doing over the last 6 months. Like most businesses we have had to adapt in 2020 to the ever-changing face of Covid. Whilst this is possible in terms of our workshop / offices, the downside for the locomotives has been very little work.
Our staple Polar Express contracts did not take place this year, nor did the Churnet Valley Railway’s Santa Express.
This year we have made big efforts to deal with long standing ‘issues’ with our locomotives. It is quite common to defer some repairs to winter or even major overhaul, as however we had plenty of spare time we have made good use of it.
Both S160’s have been in service at the Churnet Valley Railway in 2020, and to assist the railway we offered free use of our locomotives for the season.
5197
In September we discovered an old Chinese repair on the LH cylinder had failed. No doubt made up of material we are no longer able to use, we investigated various options and took 2 decisions.
Firstly, we used impregnation fluid. This is a fluid used widely in the casting / foundry world, and whilst it will never give structural strength it is thinner than water and effectively gets drawn into the molecular structure of the material and acts almost like a sealant.
This worked very well however we still need something to ‘cap it off’. Belzona came forward with a solution, and they kindly suppled a technician to come and apply it. Whilst the loco has yet to be steamed since this repair was carried out, we see no reason for any problems occurring.
One of the longer standing problems we had with the loco since its overhaul was that of valve timing. Unlike 6046, 5197 does not have a screw reverser. It is fitted with a Datong No.1 Power Reverser. We have set the valves to the measurements we have for valve travel, however clearly this was not correct.
We can only assume that under power the reverser is allowing greater movement than the drawings indicate. So, the traditional method of measuring valve travel was not going to help. We have designed with the help of some very clever volunteers at Cheddleton a method of measuring actual valve travel under power. More about this in a later update.
The loco has always run with the Chinese style lifting injectors which are loosely designed around the Nathan Simplex injector. Earlier this year our spare parts for these injectors had run out. We were able to arrange with a local CNC Company to make some new steam cones. Whilst this helped, it was clear that we needed a complete set of cones. Having limited drawings for these, and as those we do have are in Chinese we took the decision that for the moment we would not go ahead with further repairs.
Instead, we had a set of South African injectors in stock which we are in the process of fitting. As at the time the Santa Service was still due to operate, we removed the worst injector from the loco and fitted a new one, we then took the various parts we had to make one good lifting injector. It is a shame we are removing one of the final bits of its history from China, however, needs must. In the New Year we will replace the other lifting injector wit the second South African one.
A few days before Christmas the replacement tender tank was delivered for the locomotive. Following a drawn-out process, the tank was removed from the contractor carrying out the work – part completed. We will complete the work ourselves
6046
Following on from extensive inspections to take it over its 7-year boiler certificate, we were confident in the state of the boiler. As with all things related to steam locomotives nothing is simple. In September, a blowing regulator was reported at the end of the day. Investigations could find nothing wrong with the regulator valve. Further investigation found the problem to be the internal main steam pipe. It had developed a crack just behind the collar where it fits through the front tubeplate. With the Polar’s still on the cards at this stage, we stripped out the entire smokebox contents, removed the regulator and steam pipe over a weekend. Thankfully, the cancellation of Polar’s did reduce the tempo and need for speed. We hit upon a supply hiccup in delivering the new pipe from Germany.
Anyway all was rebuilt early in December and the locomotive underwent inspection. So, we have effectively carried out 2 statutory inspections in 1 year, however this will help to maximize the total length of boiler ticket remaining.
A couple of test runs took place before Christmas, and after some more adjustments it will undertake a final test run before being winterized waiting patiently for a train to pull.
3278
At long last this locomotive arrived with us in early December. It has been nearly a year since we arranged for Batt Holden to take this locomotive on, however a hold up with the turntable repairs at Tyseley and then Covid ensured a 12-month delay in its arrival.
We will finish off the locomotive and it will operate as one of ours. We won't carry out all the modifications that our own locomotives have, so this will be an odd ball as it will remain RH drive.
Spare Bogies
With 3 S160’s we have being building up our spares pool. For years we have repaired bogies using basic first principles, or generally accepted good engineering. We have spent many months researching the limits and fits for these particular ‘trucks’.
Our search for information started with a trip to Alaska in 2019, followed by many emails and exchanges of information with various knowledgeable people in the US. We now have an almost complete sets of specifications for the ‘trucks’ fitted under our S160’s. In fact it would appear we have the most comprehensive sets of documents in the world!
With all this information, we have been able to thoroughly examine our bogies under both 5197 and 6046. Whilst what we have is not dangerous, we can see divergence from how the manufacturers had intended their trucks to be assembled and maintained.
We have a set going through the workshops now and subject to successful testing we will rework all our bogies in due course.
48173
Progress on this has slowed to almost a stop over the last 6 months. Too many other jobs have ended up getting in the way of this long-term project.
However we received a boost again before Christmas with the news that the replacement axle has arrived at Riley & Sons.
After much searching and being let down by the traditional supply route, Colin Green was able to source a new axle from Belgium. We will have mussels and chips to celebrate the arrival early in the New Year.