AGL Bremerhaven Construction Update — Week 18, 2026
Construction is progressing steadily, with several key milestones reached across both warehouse halls and the surrounding infrastructure.
Current progress on site:
• The concrete floor slab in Hall 1 has been completed
• Installation of the concrete slab in Hall 2 has now started
• Canopies have been installed and fitted with safety netting
• In Hall 2, sprinkler systems are being installed, alongside lightning protection works, including mesh installation and deep earthing on the HGT layer
• Sunken loading bays (Tiefhöfe) are currently being prepared for concreting
• Curbstones and fencing are being installed across the site
• Office fit-out is nearing completion, including drywall works and cable installation
What’s next:
• Concreting of the reachstacker area scheduled for middle of May
• Installation of underfloor heating in the office building
• Screed works in the office area to follow
With interior works, technical systems, and external infrastructure progressing in parallel, the project is clearly moving into its final construction phase — bringing us closer to launching a high-performance logistics hub for pulp, paper, and heavy cargo in Bremerhaven.
More updates coming soon.